Cable manufacturing capacity is starting to become a bottleneck for the construction of data centers dedicated to artificial intelligence, Nexans says, as demand starts to impact a global supply chain already under strain.
Vincent Piquet, Chief Financial Officer at French cable maker Nexans, said cable demand is outstripping supply capacity and bottlenecks are likely to persist. This could complicate projects for developers, especially those that require "huge volumes of buildings that need to be plugged in," as tech companies are ramping up AI infrastructure.
"Adding new capacity isn't going to be the solution anytime soon. It can take three years to put in a line of cross-linked polyethylene cables, which are common in power infrastructure. Therefore, it doesn't take long for manufacturers to respond to increasing demand."
Data centers, specifically those powering AI workloads, require large volume of high and medium-voltage cables for power distribution. The growing requirements of AI are placing additional burden on cable suppliers and other electrical equipment manufacturers.
The shortfall comes as developers confront other problems, from grid-connection limits to equipment delays and permitting delays. In September, Oracle sent a force majeure notice to a unit of Blue Owl Capital, which is building a large data center complex in New Mexico, warning that "external force majeure events" may make it hard to secure enough power to operate the project.
But for Nexans, the pressure on supply is also translating into commercial benefits. Piquet said constraints in the power infrastructure sector mean that certain projects are bolstering demand for the company's products, giving it greater flexibility in how it allocates manufacturing capacity.
Demand for guaranteed cable supplies is leading customers to lock in longer-term contracts. For instance, French electricity distribution operator Enedis is now providing longer-term (six- to seven-year) contracts instead of annual supply arrangements, said Piquet. The change in approach is due to increased fears of getting enough material to build infrastructure.
There may also be regional variability in the pace of the expansion of AI infrastructure. The US has big power-related bottlenecks, whereas some areas of northern Europe have more robust electricity networks. However, Europe still has lengthy regulatory processes for certain projects, and Nexans anticipates less AI data center build in the region than the US due to differences in available private investment and public funding.
Piquet is far from convinced that demand for AI will pull back any time soon. With more investment, the availability of cables is emerging as yet another requirement to contend with in addition to hardware and electricity – and grids access.
As the shortfall increases, so does a wider difficulty for the AI industry: that investing in expensive new chips and raising money may not matter if the hardware needed to run the data centers can't be delivered fast enough.